Hastings Technology Metals Ltd (ASX:HAS) Grade Control Results Confirm Bald Hill Mineral Resource
Australia's next rare earths producer, Hastings Technology Metals Ltd (ASX:HAS) (FRA:5AM), is pleased to announce results from the Bald Hill grade-control drilling campaign, completed as part of the 2020 Drilling Program at its Yangibana Rare Earths Project (Yangibana) in Western Australia's Gascoyne region.

Highlights

- Grade-control drilling comprising 257 holes for 5,002m has been completed at Bald Hill, the largest deposit at the Yangibana Rare Earths Project and containing approximately 39% of the Yangibana Project's total Mineral Resources.

- Correlation of tonnes, grades and total rare earth oxides (TREO) between the Yangibana Project Mineral Resource Upgrade (announced 5 May 2021) and the trial grade control model has been completed.

- The strong reconciliation confirms and exceeds the results for the same area from the Bald Hill Mineral Resource estimate by delivering:
o 6% more TREO; and
o 9% more resource tonnes

- Drilling results provide Hastings with significantly increased confidence in the target area earmarked for first Yangibana Project mine production and allow for more accurate delineation of ore and waste boundaries, with Bald Hill drill intercepts including;
o 7m @ 2.73% TREO from 5m, GC0434
o 4m @ 3.15% TREO from 10m, GC0291
o 5m @ 2.65% TREO from 12m, GC0268
o 5m @ 2.39% TREO from 8m, GC0312.

- The Yangibana Project's Mineral Resource estimate stands at 27.42Mt @ 0.97% TREO for 266kt of rare earth oxides (ASX Announcement 5 May 2021).

The grade control drilling campaign (Figure 2*) was designed to test-drill a shallow area of mineralisation at the Bald Hill deposit, with all holes drilled to a targeted level below the natural surface. A close-spaced reverse circulation (RC) drill pattern of 5mE x 7mN was completed, with 257 holes for 5,002m being drilled.

This campaign targeted a zone within the first 20m (eight mining benches) from surface, containing enough material to define short-term mine planning at the start of production for a two-month period. Table 1* shows the comparison between the Bald Hill Mineral Resource estimate and the grade-control model within the area of the grade-control drilling.

The comparison suggests a slight increase in both tonnes and contained metal with only a minor loss of grade for both TREO and Nd2O3 + Pr6O11. The Mineral Resource estimate for Bald Hill used for this comparison was previously announced to the ASX by the Company on 5 May 2021 (see ASX announcement Yangibana Project updated Measured and Indicated Mineral Resources tonnes up by 54%, TREO oxides up 32%).

A grade tonnage comparison between the grade-control model and the Mineral Resource estimate is shown in Figure 1* and indicates a strong correlation between both estimates. It should be noted that because the grade-control drilling was sampled in its entirety, there is more definition in the low-grade tail than what appeared in the Mineral Resource estimate due to the selective nature of the exploration sampling.

Commenting on the results of the grade-control drilling at Bald Hill, Hastings Technology Metals' Chief Operating Officer Andrew Reid said: "The reconciliation provides confidence that close-spaced, grade-control drilling reflects our Mineral Resource estimates, which further mitigates the start-up risk for our Yangibana Rare Earths Project. "These initial results indicate the potential for more tonnage and more contained rare earth oxides within the Bald Hill starter pit, which potentially reduces the strip ratio at the beginning of the mine life, as well as providing substantially more data to optimise mine planning. "The strong continuity of mineralisation defined by the grade-control drilling at the start of the mine life provides a high level of confidence during mine start-up."

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/52UF4KY8

Charles Lew 
Chairman 
T: +65-6220-9220 /+61-8-6117-6118

Andrew Reid
Chief Operations Officer
T: +61-487-888-787





Disclaimer | Terms Of Use And Privacy Statement


© Metals News. All rights reserved.